I-15; Farr West to Brigham City
- Owner: UDOT
- Location: I-15; 2700 N to 1100 S
- Project Manager: Daniel Bird / Mike Westbroek
- General Contractor: Geneva Rock
- Core Competencies:
Earthwork, Pipelines & Drainage, Demolition, Asphalt Paving, Ready-Mix Concrete, Utilities - Year: August 2017
The I-15 North of Brigham City consisted of widening 26 lane miles of road widening on I-15 from Farr West to Brigham City, Utah. This project included the widening of 8 bridges with new drainage, pipe lining, new retaining barrier wall the entire 13 miles corridor and reconstruction of the Port of Entry in Box Elder County. The pavement section was 6 inches of road base, with 3 inches of HMA, and 9 inches of PCCP. All pavement markings removed and replaced as part of a large change order. There were additional change orders for a bonded wearing course on the last 2 miles of the project the full width of I-15.
The total project time bid was 270 calendar days. Geneva Rock achieved substantial completion in 240 days at a daily rate of $30,000 per day incentive.