US-93 Salmon Idaho Chip Seal
Date

November 10, 2016

Category

Projects

This job is an 86 mile chip seal project along the Salmon River in Salmon, Idaho and running up to the Montana border. This is one of three different chip seal contracts awarded to Geneva Rock totaling nearly 300 lane miles of chip seal to be completed for the Idaho Transportation Department during the 2016 season.
Start Date: June 28, 2016
End Date: August 31, 2016
Combined SY: 2,363,016
Oil Sprayed: 4,500 tons
Aggregate placed: 33,000 tons
  • Runway and Taxiway Pavement Rehabilitation

     Salt Lake City Department of Airports required upgrade and a pavement rehabilitation on several of their runways (16-34). Taxiway ‘A’ was reconstructed, then milled and paving was completed on the runways and taxiway.

  • I-80; Silver Creek to Wanship

    Innovation, technology and environmental consciousness are of the highest importance at Geneva Rock. These were vital standards during the I-80 Silver Creek to Wanship project that was recently completed. UDOT teamed up with Geneva Rock to replace this 7 1/2 mile stretch of I-80 that had corroded due to the high altitude and harsh environment.

  • Lehi City Waste Ditch Improvements

    The city of Lehi, Utah sought to increase the allowable amount of water their municipal drainage ditch could handle. The Lehi City Wast Ditch Improvements project includes removal of  four existing pipe culverts, replacing them with pour-in-place box culverts.  Utilities and asphalt paving work is also being completed at the end of the project to improve the surrounding areas. Geneva