I-15; Choke Point
Owner

UDOT

Location

I-15 in Davis County

Core Competencies

Earthwork, Pipelines & Drainage, Demolition, Asphalt Paving, Utilities

Date Completed

April 2017

The I-15 Choke Point project consisted of adding an auxiliary lane on southbound I-15 from Layton Parkway to 200 North in Kaysville, and an auxiliary lane northbound I-15 from the Kaysville rest area to Layton Parkway. This particular section of I-15 is extremely congested and is considered a very high risk area of work due to the limited amount of traffic visibility to the construction zones – especially in the southbound section.
The original timeline for the project had a schedule of 80 days to complete. One of the major portions of the work was the southbound widening which included the reconstruction of the MSE wall with integrated storm drain along the UTA and UP track lines. Along with this scope of work, median storm drainage work was also required in the southbound direction. This area played an integral role in the scheduling and constructability due to the limited amount of traffic control that was allowed on the project. In addition to the traffic control, UTA had their own set of constructability time frames and regulations that were required.
Overall with the limited amount of traffic control and lanes needed for safety in such a high risk area, finishing the project on time with zero accidents was a significant achievement.
  • Lehi City Waste Ditch

    The city of Lehi, Utah sought to increase the allowable amount of water their municipal drainage ditch could handle. The Lehi City Wast Ditch Improvements project includes removal of  four existing pipe culverts, replacing them with pour-in-place box culverts.  Utilities and asphalt paving work was also completed at the end of the project to improve the surrounding areas. Geneva

  • I-15; Davis County

    UDOT commissioned Geneva Rock to rotomill out 1-1/2″ of existing asphalt on I-15 and replace with 1″ of Bonded Wearing Course (BWC) sprayed onto the pavement. Geneva Rock is the first company to use the Roadtec Spray Paver in Utah. BWC is an industry-leading technology that delivers a durable, open-graded, drainable surface with a lifespan of

  • I-80; 1300 E to I-215 Interchange

    The project runs 7 days per week night and day with multiple lane restrictions during both day and night. This is a maintenance project as UDOT will put out to bid in 10 years to re-build the whole project.