Salt Lake City International airport redevelopment ready mix concrete paving

This portion of the Salt Lake City International Airport new terminal development project included 4 taxiway intersection reconstructions, additional apron paving and channel drain installation that were all under strict time restraints and were successfully completed ahead of schedule. This phase consisted of 2 separate projects which are both part of the new terminal redevelopment at the Salt Lake City Airport. The work started in 2018 and will continue into the 2021.
The 4 taxiway projects encompass in this phase used:

    • 399,000 square yards of lean concrete
    • 390,000 square yards of portland cement concrete pavement (PCCP)
    • 5400 linear feet of channel drain